Obsolete PLCs and drives in 2027: an obsolescence checklist for Indian plants

Many PLC and drive families are leaving production. A 2027 checklist to find your obsolete parts, protect programs, test spares and plan repair or upgrade.

Rajiv Tomar, DirectorPublished 5 min read

Key takeaways

  • Find out the lifecycle status of every critical controller, drive and HMI, by catalogue number, from the manufacturer.
  • A tested spare and a backed-up program turn most failures into a swap.
  • Repair buys time. Plan any migration for a scheduled shutdown.
  • Review the list every year, because status changes.

The CPU on a filling line stops with a fault light on a Tuesday night. The maintenance engineer goes to the store for the spare and finds an empty box with a note: “issued 2019”. The local distributor says the part is discontinued. The program on the CPU’s memory card was last copied by a contractor who no longer answers the phone.

That chain of small gaps is what turns a module failure into a week of lost production. None of it is about the failed CPU itself. It is about not knowing, in advance, which parts are leaving the market and what you would do when they fail.

This checklist is for the audit itself: a structured way to go through your plant in 2027, find the obsolete and soon-to-be-obsolete parts, and decide what to do about each one. Our earlier article on repairing or replacing obsolete modules covers the decision when a part has already failed.

How manufacturers retire products

Automation manufacturers don’t stop making a product overnight. Most follow a series of lifecycle stages, though the names differ from one company to another:

  1. Active. The product is sold and supported normally.
  2. Phase-out announced. The manufacturer has said the product will be withdrawn and usually names a successor. It is still on sale.
  3. Cancelled for new sales. You can no longer order it as a new product for a new project.
  4. Spares only. The manufacturer still supplies replacement units or repairs for a period, often at longer lead times.
  5. Discontinued. No supply or support from the manufacturer.

A well-known example is the Siemens S7-300 PLC family. Siemens announced its phase-out in October 2023, product cancellation followed in October 2025, and spare parts are expected to be available until about October 2033, according to the manufacturer at the time of writing. Many Indian plants still run S7-300 systems, so it is a good illustration: a controller can be “cancelled” yet still have years of spares support ahead of it, and the time to plan is during those years, not after them.

Dates differ for every family and sometimes for individual catalogue numbers within a family. Always check your own parts.

Step 1: list what you run

Walk the plant, panel by panel. For each programmable or power electronic item, record:

  • the machine or line it belongs to
  • the manufacturer, model and full catalogue number (from the label, not from old drawings)
  • firmware or hardware version, if shown
  • how many identical units you have across the site
  • what happens if it fails: does the line stop, slow down, or carry on?

Include the parts people forget: HMIs, communication modules, power supplies, servo drives, encoder interface cards and remote I/O. A line can stop just as surely for a failed communication card as for a failed CPU.

Step 2: check status by catalogue number

For each catalogue number, find its lifecycle status from the manufacturer. Most large manufacturers have an online lifecycle or product-status search, or your distributor can confirm it in writing. Record the stage, any announced dates and the suggested successor.

Be careful with general statements such as “the whole range is discontinued”. Status is set by catalogue number. Two modules that look alike may be at different stages.

Then mark each line on your list:

  • Red: discontinued or spares only, and its failure stops production.
  • Amber: phase-out announced or cancelled for new sales, or red items that don’t stop production.
  • Green: active.

Step 3: back up programs and parameters

A failed module can usually be repaired or replaced. A lost program often can’t be rebuilt without weeks of work. For every programmable item:

  • Upload and save the PLC program, drive parameters and HMI project.
  • Record the software version needed to open each file, and keep the cable and adapter needed to connect.
  • Store two copies in different places and note the date of each backup.
  • Check memory backup batteries on older controllers, if fitted. Replace them at the manufacturer’s interval, with power applied if the manual says so, so the program isn’t lost during the change.

Step 4: test and store spares

A spare you haven’t tested is a hope, not a spare.

  • Confirm that each red and amber item has a spare, and that the spare’s catalogue number and version actually match what is installed.
  • Power-test stored spares on a schedule, following the manufacturer’s guidance. Drives and power supplies that have sat unpowered for years may need their capacitors reformed before full voltage is applied; the manual explains how.
  • Store spares dry, in anti-static packaging, labelled with what they are for and when they were last tested.

Step 5: decide repair, spare or migration for each item

For every red and amber item, choose one of four paths and write it down:

Path When it fits
Keep a tested spare The part is still obtainable, new or refurbished, and the machine has years of life left
Rely on repair The part can be repaired at component level and you can tolerate the repair time; ideally combined with a spare
Plan a migration The system is critical, spares are drying up, and the machine will run for many more years
Design a replacement No direct successor fits, and a custom interface or replacement board is the practical route

Repair is often the fastest way back into production for an obsolete module, subject to inspection and to parts being available. It keeps wiring, programs and parameters unchanged. But it buys time; it doesn’t stop the clock. Where a whole system is near the end of its supported life, plan a migration for a scheduled shutdown, with time to convert and test the program, rather than doing it under pressure after a failure.

Where nothing on the market fits, a custom replacement designed to match the existing connections can keep an older machine running.

Make the review annual

Lifecycle status changes. A part that was active this year may be announced for phase-out next year. Put the obsolescence review into your yearly maintenance plan, in a quiet month, and update the list each time.

If you need help with the audit, with testing spares, or with component-level repair of obsolete modules, send us your list and we’ll tell you what we can repair.

General guidance based on common engineering practice. Always follow the equipment manufacturer’s instructions and your site’s safety procedures.

Add RATOM as a preferred source on Google

Related services

How we can help.

Keep reading

More from our engineers.

Got a unit that’s down?

Tell us the make, model and fault, and we’ll reply within one working day with questions or next steps.